Building an MVP: a guide from 7 real products

In seven products I've led, the first release (a launch, a beta or, once, a full prototype) came 5 to 16 weeks after kickoff. Scope decided where each one landed in that range: how much had to be built, how much an existing tool could do, and how much had to be right on day one, more than how big the team was.

The timelines run from SportsOnTV, a sports channel and news site that went live in 5 weeks against an 8-week plan, to SmartPeople, an HR and payroll platform that held a fixed 16-week plan to get ready for launch. In between are Varsee's full prototype in 6 weeks, LeanDeck's beta with 6 agencies in 8 weeks, Mark Andrews Creative live in 12 weeks, and Find Your Calm and KpiClock at about three months each.

The fast ones integrated before they built, kept the first release to one job and put money on fixed rules. The long ones had money and access rules that had to work at launch, replaced a system a business used every day, or had to be several products at once.

This guide puts the posts in the order I'd use them on a new product. It starts with the timelines, then the scope: what goes into the first release and what moves after it. Next comes discovery, which turns a one-sentence brief into goals, users and rules, and the PRD that writes those rules down for developers. Then the build itself: the integrate-first approach that put SportsOnTV live in 5 weeks, the ten checks I run before a launch, and the switch-over plan for an MVP that replaces a system customers already use. It ends with the people question: whether to bring in a product manager, a product designer, or one person who does both.

Each post stands on its own, and each comes from a real product with a case study on this site. The PRD template and the MVP scope worksheet are free at the end.

The guide

8 posts, in reading order

  1. Step 1 of 8

    Start with the question every plan starts with. Seven real timelines show which end of the 5-to-16-week range your product is likely to land at, and why.

    No. 02030 Oct 2026

    How long does it take to build an MVP? Real timelines from 7 products

    Seven products I led, from a 5-week launch to a 16-week plan. What made the fast ones fast, what made the long ones long, and how to estimate yours.

    Product Management · 7 min
  2. Step 2 of 8

    Once you know what drives the time, scope is how you control it. This is the six-step method for deciding what goes into the first release and what moves after it.

    No. 01930 Oct 2026

    How to scope an MVP: what to build first and what to cut

    A six-step method for deciding what goes into a first release, with the real cuts I made on KpiClock, SmartPeople, LeanDeck and Mark Andrews Creative.

    Product Management · 7 min
  3. Step 3 of 8

    Scope needs answers to cut against. Discovery turns a one-sentence brief into goals, users, rules and success metrics before anything is built.

    No. 01130 Oct 2026

    Product discovery for startups: a process for when the brief is one sentence

    How I turn a one-line idea into goals, users, rules and a buildable scope, from the discovery work on Mark Andrews Creative, LeanDeck and Find Your Calm.

    Product Management · 6 min
  4. Step 4 of 8

    The answers from discovery have to end up somewhere developers can build from. A PRD is that place, and this post comes with a free two-page template.

    No. 01830 Oct 2026

    How to write a PRD developers can build from (free template)

    The sections a product requirements document needs, how to write business rules nobody has to guess, and a free two-page PRD template.

    Product Management · 7 min
  5. Step 5 of 8

    With the scope and rules written, the biggest time saver is what you don't build. SportsOnTV went live in 5 weeks by using proven tools for everything that wasn't its core.

    No. 00730 Oct 2026

    Live in 5 weeks against an 8‑week plan: integrate before you build

    SportsOnTV, a 24/7 sports channel and news hub covering 32 sports, went live in five weeks against an eight-week plan. We used proven tools wherever we could and built only what had to be ours.

    Product Management · 4 min
  6. Step 6 of 8

    Before launch, run the ten checks, from success metrics agreed before the build to time planned for what real use shows.

    No. 00830 Oct 2026

    A launch‑readiness checklist for SaaS products

    Ten checks I'd run before any SaaS launch, each one learned on a real product, from measuring the old system to the first weeks after launch. With a one-page PDF.

    Product Management · 4 min
  7. Step 7 of 8

    If your MVP replaces a system customers already use, the switch-over needs its own plan. This is the checklist from moving Rooftop Saunas onto Find Your Calm while bookings kept flowing.

    No. 01030 Oct 2026

    How to move customers to a new SaaS platform without downtime

    A switch-over checklist from moving Rooftop Saunas onto Find Your Calm, where bookings kept flowing the whole way through.

    Product Management · 6 min
  8. Step 8 of 8

    Last, the people question: who to bring in first, and when one person can decide what to build and design it too.

    No. 00930 Oct 2026

    Product manager vs product designer: what each does, and when one person can do both

    What a product manager and a product designer each do, where the roles overlap, and when an early team gains from one person doing both.

    Product Management · 6 min
Case studies

The products behind it

Free

Free templates

Questions

Frequently asked questions

Building a product?

I help founders and teams decide what to build, design it, and ship it. Tell me about your project.