Building an MVP: a guide from 7 real products
In seven products I've led, the first release (a launch, a beta or, once, a full prototype) came 5 to 16 weeks after kickoff. Scope decided where each one landed in that range: how much had to be built, how much an existing tool could do, and how much had to be right on day one, more than how big the team was.
The timelines run from SportsOnTV, a sports channel and news site that went live in 5 weeks against an 8-week plan, to SmartPeople, an HR and payroll platform that held a fixed 16-week plan to get ready for launch. In between are Varsee's full prototype in 6 weeks, LeanDeck's beta with 6 agencies in 8 weeks, Mark Andrews Creative live in 12 weeks, and Find Your Calm and KpiClock at about three months each.
The fast ones integrated before they built, kept the first release to one job and put money on fixed rules. The long ones had money and access rules that had to work at launch, replaced a system a business used every day, or had to be several products at once.
This guide puts the posts in the order I'd use them on a new product. It starts with the timelines, then the scope: what goes into the first release and what moves after it. Next comes discovery, which turns a one-sentence brief into goals, users and rules, and the PRD that writes those rules down for developers. Then the build itself: the integrate-first approach that put SportsOnTV live in 5 weeks, the ten checks I run before a launch, and the switch-over plan for an MVP that replaces a system customers already use. It ends with the people question: whether to bring in a product manager, a product designer, or one person who does both.
Each post stands on its own, and each comes from a real product with a case study on this site. The PRD template and the MVP scope worksheet are free at the end.
8 posts, in reading order
-
Step 1 of 8
Start with the question every plan starts with. Seven real timelines show which end of the 5-to-16-week range your product is likely to land at, and why.
No. 02030 Oct 2026How long does it take to build an MVP? Real timelines from 7 products
Seven products I led, from a 5-week launch to a 16-week plan. What made the fast ones fast, what made the long ones long, and how to estimate yours.
Product Management · 7 min -
Step 2 of 8
Once you know what drives the time, scope is how you control it. This is the six-step method for deciding what goes into the first release and what moves after it.
No. 01930 Oct 2026How to scope an MVP: what to build first and what to cut
A six-step method for deciding what goes into a first release, with the real cuts I made on KpiClock, SmartPeople, LeanDeck and Mark Andrews Creative.
Product Management · 7 min -
Step 3 of 8
Scope needs answers to cut against. Discovery turns a one-sentence brief into goals, users, rules and success metrics before anything is built.
No. 01130 Oct 2026Product discovery for startups: a process for when the brief is one sentence
How I turn a one-line idea into goals, users, rules and a buildable scope, from the discovery work on Mark Andrews Creative, LeanDeck and Find Your Calm.
Product Management · 6 min -
Step 4 of 8
The answers from discovery have to end up somewhere developers can build from. A PRD is that place, and this post comes with a free two-page template.
No. 01830 Oct 2026How to write a PRD developers can build from (free template)
The sections a product requirements document needs, how to write business rules nobody has to guess, and a free two-page PRD template.
Product Management · 7 min -
Step 5 of 8
With the scope and rules written, the biggest time saver is what you don't build. SportsOnTV went live in 5 weeks by using proven tools for everything that wasn't its core.
No. 00730 Oct 2026Live in 5 weeks against an 8‑week plan: integrate before you build
SportsOnTV, a 24/7 sports channel and news hub covering 32 sports, went live in five weeks against an eight-week plan. We used proven tools wherever we could and built only what had to be ours.
Product Management · 4 min -
Step 6 of 8
Before launch, run the ten checks, from success metrics agreed before the build to time planned for what real use shows.
No. 00830 Oct 2026A launch‑readiness checklist for SaaS products
Ten checks I'd run before any SaaS launch, each one learned on a real product, from measuring the old system to the first weeks after launch. With a one-page PDF.
Product Management · 4 min -
Step 7 of 8
If your MVP replaces a system customers already use, the switch-over needs its own plan. This is the checklist from moving Rooftop Saunas onto Find Your Calm while bookings kept flowing.
No. 01030 Oct 2026How to move customers to a new SaaS platform without downtime
A switch-over checklist from moving Rooftop Saunas onto Find Your Calm, where bookings kept flowing the whole way through.
Product Management · 6 min -
Step 8 of 8
Last, the people question: who to bring in first, and when one person can decide what to build and design it too.
No. 00930 Oct 2026Product manager vs product designer: what each does, and when one person can do both
What a product manager and a product designer each do, where the roles overlap, and when an early team gains from one person doing both.
Product Management · 6 min
The products behind it
Free templates
PRD template
The nine parts of a PRD, with space to write each one: problem, users, scope, flows, business rules, edge cases, data, success metrics and open questions. A two-page PDF: subscribe, and it’s yours to download here.
Read the postYou're in. Check your inbox. Download the PRD template PDF
One email when a post is out. No spam. Unsubscribe any time.
Something went wrong. Please email iftiak.ad@gmail.com and I'll add you.
MVP scope worksheet
One page to scope a first release: the job people will do every day, the must-have flows, where money moves, what to integrate, what to cut, what comes after launch and how you will measure success. A one-page PDF: subscribe, and it’s yours to download here.
Read the postYou're in. Check your inbox. Download the MVP scope worksheet PDF
One email when a post is out. No spam. Unsubscribe any time.
Something went wrong. Please email iftiak.ad@gmail.com and I'll add you.
Frequently asked questions
How long does it take to build an MVP?
In my projects, a first launch or beta took 5 to 16 weeks. SportsOnTV went live in 5 weeks, LeanDeck reached its beta in 8, Mark Andrews Creative went live in 12, and SmartPeople held a fixed 16-week plan. Scope set the time more than team size did.
What should you cut from an MVP?
Keep the part people use every day, complete, and keep money paths on fixed rules. Move other modules, extra billing options, most reports and settings, and anything an existing tool already does. On SmartPeople, cutting about 30% of modules, features and reports let a fixed 16-week plan hold.
What should a PRD include?
Nine sections: problem, users, scope, flows, business rules, edge cases, data, success metrics and open questions. Write every business rule in the same shape: when [situation], [who] can [do what], up to [limit]; otherwise, [what happens].
How do you move customers to a new platform without downtime?
Track the old system first, agree the main metric and its time window, map every path, move all the data and test every path, then switch only when the new system covers everything. On Find Your Calm, bookings kept flowing through the switch-over.